PM-KUSUM Yojana - Solar Energy Scheme | IBEF (2024)

Introduction

The Pradhan Mantri Kisan Urja Suraksha evem Utthan Mahabhiyan (PM-KUSUM) scheme received approval from the Cabinet Committee on Economic Affairs and was launched in March 2019 to secure energy and water for farmers, increasing their earnings, transitioning away from diesel in agriculture and reducing environmental pollution. In September 2023, the scheme expanded, a decision approved by the Ministry of Finance, and was extended until March 2026. The PM-KUSUM scheme permits the transfer of quantities between Component-B and Component-C. All three components of the scheme aim to add approximately 34,800 MW of solar capacity by March 2026. This is supported by a total central financial allocation of Rs. 34,422 crore (US$ 4.12 billion).

PM-KUSUM Yojana - Solar Energy Scheme | IBEF (1)

Scheme components

The scheme comprises the following components:

  1. Component-A: Installation of 10,000 MW of decentralised ground- or stilt-mounted grid-connected solar power plants or other renewable energy-based power plants. Individual farmers, cooperatives, panchayats, solar power developers and farmers' producer organisations can all install these plants.
  2. Component-B: Installation of 14 lakh standalone off-grid solar water pumps.
  3. Component-C: Solarisation of 35 lakh existing grid-connected agriculture pumps through (i) solarising individual pumps and (ii) solarising at the feeder level.

Components B and C could benefit individual farmers, water user associations, primary agriculture credit societies and community-/cluster-based irrigation systems.

Financial support

The PM-KUSUM scheme provides Distribution Companies (DISCOMs) with a Procurement-Based Incentive (PBI) to buy solar or other renewable energy. The price at which the PBI is offered is 40 paise per kWh or Rs. 6.60 lakh (US$ 7,904) per megawatt (MW) per year, whichever is less. The renewable energy plant's commercial operation date is followed by a five-year term during which the DISCOMs are granted this PBI. Thus, for every MW of solar or other renewable power purchased, the total PBI payable to DISCOMs is Rs. 33 lakh (US$ 39,518) per MW.

For Component-B and solarisation of individual pumps under Component-C:

Farmers are offered financial support that amounts to 30% of the benchmark cost set by the Ministry of New and Renewable Energy (MNRE) or the prices decided through the tender process, whichever is lower. However, in the northeastern states, including Sikkim, Jammu & Kashmir, Ladakh, Himachal Pradesh, Uttarakhand, Lakshadweep, and Andaman & Nicobar Islands, a higher support of 50% of the benchmark cost set by the MNRE or the prices discovered in the tender, whichever is lower, is extended to the farmers.

Furthermore, the respective state/UT must furnish a minimum of 30% financial assistance. The remaining cost is to be covered by the beneficiary. Components B and C (IPS) of the PM-KUSUM scheme can be executed even without the state's 30% share. The Central Financial Assistance (CFA) will remain at 30%, with the farmer bearing the remaining 70%.

A financial assistance of Rs. 1.05 crore (US$ 125,733) per MW is allocated for the solarisation of agricultural feeders. There is no obligatory need for financial backing from the involved state/UT. Feeder solarisation can be executed either in CAPEX or RESCO mode.

Progress under PM-KUSUM (as on 31.01.2024)

S.No.StateComponent-A (MW)Component-B (Nos)Component-C (Nos)
SanctionedInstalledSanctionedInstalledSanctioned (IPS)Sanctioned (FLS)Installed
1Arunachal Pradesh20700199000
2Assam1004,00001,00000
3Chhattisgarh30110,00000157,5000
4Bihar00000160,0000
5Gujarat50008,0822,4590625,5000
6Goa15009000011,000700
7Haryana852.25252,65580,004065,0790
8Himachal Pradesh10022.91,270638000
9Jammu & Kashmir2005,0008384,00000
10Jharkhand20042,98512,9851,00000
11Karnataka0027,2143140587,0000

12

Kerala

40

100

8

55,100

25,387

2,824

13

Ladakh

1,400

14

Madhya Pradesh

600

16.13

22,400

7,134

295,000

15

Maharashtra

700

2

405,000

79,118

775,000

1,979

16

Manipur

150

78

17

Meghalaya

3,035

54

18

Mizoram

2,700

19

Nagaland

5

265

65

20

Odisha

500

8,241

1,411

65,000

10,000

21

Puduch*erry

22

Punjab

220

103,000

12,952

186

75,000

23

Rajasthan

1,200

121

248,720

59,732

6,418

200,000

1,811

24

Tamil Nadu

424

5,200

3,187

25

Telangana

400

20,000

26

Tripura

5

10,895

2,117

2,600

50

27

Uttar Pradesh

155

114,790

32,212

2,000

370,000

28

Uttarakhand

5,685

318

200

29

West Bengal

10,000

23,700

20

Total

4,766

165.28

1,294,787

295,823

161,204

3,376,466

7,384

Steps taken by the ministry for proper implementation of PM-KUSUM include:

  • CFA is currently offered for pump capacities up to 15 HP (raised from 7.5 HP) for individual farmers residing in northeastern states, hilly states/UTs and island UTs. Furthermore, every farmer participating in cluster/community irrigation initiatives in regions with high water tables, spanning across states/UTs, qualifies for CFA.
  • Discussions have been held with banks/FIs to ensure low-cost financing options for farmers.
  • State-level tenders are permitted for standalone solar pump procurement.
  • The implementation timeline has been extended to 24 months from the initial sanction date.
  • The requirement for performance bank guarantees has been relaxed under Component-A and Component-C.
  • Tender conditions have been revised to broaden the installer base for quicker scheme implementation.
  • Solarisation of pumps under Components B and C is now included in the Agriculture Infrastructure Fund (AIF) to provide financed loans to farmers.
  • The scheme is now part of the Reserve Bank of India's (RBI) Priority Sector Lending (PSL) Guidelines, making it easier for people to get loans.
  • Specifications and testing procedures for solar pumps have been continually revised to confirm installation quality.
  • Web portals have been developed at the central and state levels for scheme monitoring.
  • Publicity and awareness efforts, including through CPSUs, are being undertaken.
  • A toll-free number has been provided for easy access to scheme information.
  • Progress is regularly monitored, and clarifications and amendments to the scheme guidelines are issued based on implementation lessons.
  • Extension is granted for projects sanctioned under the scheme based on achieved progress and milestones.
  • Scheme guidelines were simplified on July 12, 2023, to streamline the land aggregation process in Component-C.
  • Benchmark costs were issued under Component-B in September 2023.
  • The mandatory state share provision was removed from the scheme through an OM dated November 20, 2023.
  • The waiver of DCR content in Component-C was prolonged until March 31, 2024, according to an OM issued on September 11, 2023.
  • The Department of Expenditure (DoE) raised the target from 35 lakh to 49 lakh for Composite B and C after issuing an OM on September 6, 2023.

The road ahead

The scheme promises to establish a dependable and consistent revenue stream for rural landowners over a span of 25 years by making use of their dry or uncultivated land. Moreover, in case cultivated fields are selected for installing solar power projects, farmers can continue farming as solar panels will be installed at a height above the ground to allow farming of crops.

The scheme aims to ensure a sufficient supply of solar or other renewable energy-based power is available locally to meet the energy needs of rural areas and agricultural pump sets, which typically require power during daytime. Situating these power plants nearer to agricultural loads or electrical sub-stations in a decentralised fashion will lead to lower transmission losses for STUs and DISCOMs. Additionally, the scheme will aid DISCOMs in achieving their Renewable Purchase Obligation (RPO) targets.

Solar pumps will not just cut costs linked to diesel use for running pumps but also provide farmers with a reliable irrigation option. This helps minimise pollution caused by diesel pumps. With a long queue for electric grid connections, this plan will help 17.5 lakh farmers in four years, without adding pressure on the grid.

PM-KUSUM Yojana - Solar Energy Scheme | IBEF (2024)
Top Articles
Topics | Dangerous Minds
Anatomy Drawing Lessons
9.4: Resonance Lewis Structures
It's Official: Sabrina Carpenter's Bangs Are Taking Over TikTok
Wal-Mart 140 Supercenter Products
ds. J.C. van Trigt - Lukas 23:42-43 - Preekaantekeningen
Bbc 5Live Schedule
Mid90S Common Sense Media
Springfield Mo Craiglist
Leader Times Obituaries Liberal Ks
Extra Virgin Coconut Oil Walmart
Trac Cbna
Vipleaguenba
Ge-Tracker Bond
Lola Bunny R34 Gif
Hdmovie2 Sbs
Adt Residential Sales Representative Salary
The Old Way Showtimes Near Regency Theatres Granada Hills
2021 Volleyball Roster
Www.patientnotebook/Atic
Xfinity Outage Map Fredericksburg Va
Lost Pizza Nutrition
Troy Gamefarm Prices
Lovindabooty
Cona Physical Therapy
CohhCarnage - Twitch Streamer Profile & Bio - TopTwitchStreamers
Helloid Worthington Login
What Is The Lineup For Nascar Race Today
Powerball lottery winning numbers for Saturday, September 7. $112 million jackpot
Craigslist Org Sf
All Things Algebra Unit 3 Homework 2 Answer Key
Seymour Johnson AFB | MilitaryINSTALLATIONS
Barrage Enhancement Lost Ark
Domino's Delivery Pizza
Louisville Volleyball Team Leaks
Aveda Caramel Toner Formula
Regis Sectional Havertys
Myanswers Com Abc Resources
Review: T-Mobile's Unlimited 4G voor Thuis | Consumentenbond
Cranston Sewer Tax
Lovein Funeral Obits
Uvalde Topic
Brandon Spikes Career Earnings
Citibank Branch Locations In North Carolina
Panolian Batesville Ms Obituaries 2022
10 Types of Funeral Services, Ceremonies, and Events » US Urns Online
Rheumatoid Arthritis Statpearls
Who uses the Fandom Wiki anymore?
Bismarck Mandan Mugshots
Campaign Blacksmith Bench
Grace Charis Shagmag
Dcuo Wiki
Latest Posts
Article information

Author: Catherine Tremblay

Last Updated:

Views: 5639

Rating: 4.7 / 5 (47 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Catherine Tremblay

Birthday: 1999-09-23

Address: Suite 461 73643 Sherril Loaf, Dickinsonland, AZ 47941-2379

Phone: +2678139151039

Job: International Administration Supervisor

Hobby: Dowsing, Snowboarding, Rowing, Beekeeping, Calligraphy, Shooting, Air sports

Introduction: My name is Catherine Tremblay, I am a precious, perfect, tasty, enthusiastic, inexpensive, vast, kind person who loves writing and wants to share my knowledge and understanding with you.